The 11th floor of the building was the first occupancy. This floor was the future home to the executives of National Penn Bank. It took less than 11 months from installation of foundations to achieve this goal. We were also 6 weeks ahead of schedule.
by gudrunfrank | Jan 16, 2021
Through our unique ability to safely coordinate trades we had (5) major trades working together on structural and the facade simultaneously. Through unparalleled cooperation and respect in our planning ability, we were able to get to erect steel, poor concrete floor,...
by gudrunfrank | Jan 15, 2021
In five months time, we went from concept idea to acquiring all government approvals. At the same time, demolition took 12 weeks to remove and dispose of an existing six story building.
by gudrunfrank | Jan 15, 2021
On January 10th, 2014, we received our first CO which included occupancy of the 11th floor and finished spaces in the core and shell of the building.
by gudrunfrank | Jan 15, 2021
The entire structure was completed in 13 weeks. In less than 9 months time, from start of foundation, we were able to start the interior improvements in a 100% dry and permanent power fed building.